Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : NEW BG LINE FROM JAGBANI TO BIRATNAGAR.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   66.3

Time Overrun (Months)-    24279

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
241.520401.65

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
343.300343.3

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/03/2023

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
10

Ministry Review Date

LatestLastPhysical Progress (%)Status
85.42Ongoing

Monthly Status

Background Information

"""Land between Km 16.80 to Km. 18.60 including Biratnagar Yard handed over by Nepalese Authorities on 03.11.2019. Now 100% land is available for the project. -78% earthwork, 82% Blanketing, all three major bridges and 27 out of total 29 minor bridges completed. - track linking completed in Bathnaha - Nepal Custom Yard section except goods lines. -Revised estimate of Rs. 373.87 cr. submitted to MEA, yet to be sanctioned. DRM / KIR along with his team visited upto ICY on the proper signalling system by his inspection vehicle on 07.09.2022 so that further goods train can run upto NCY and assets could be utilized. After NI, Bathnaha Yard has been commissioned on 12-13 June, 2022 "

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone