Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 66.3
|
Time Overrun (Months)-
24279
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| """Land between Km 16.80 to Km. 18.60 including Biratnagar Yard handed over by Nepalese Authorities on 03.11.2019. Now 100% land is available for the project.
-78% earthwork, 82% Blanketing, all three major bridges and 27 out of total 29 minor bridges completed.
- track linking completed in Bathnaha - Nepal Custom Yard section except goods lines.
-Revised estimate of Rs. 373.87 cr. submitted to MEA, yet to be sanctioned. DRM / KIR along with his team visited upto ICY on the proper signalling system by his inspection vehicle on 07.09.2022 so that further goods train can run upto NCY and assets could be utilized.
After NI, Bathnaha Yard has been commissioned on 12-13 June, 2022
" |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |