Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EAST FRONTIER RAILWAY.
Project Name : MURKONGSELEK-PASIGHAT NL.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   186.25

Time Overrun (Months)-    60

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
414.8401187.49

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
347.15102.1223.38472.65

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
4000

Ministry Review Date

LatestLastPhysical Progress (%)Status
18Ongoing

Monthly Status

Background Information

Land Acquisition (Hect.) : (Scope= 172.31/Physical progress= 167.945) = 97.47% Earth Work (Lakh Cum.) : (Scope= 18.21/Physical progress= 10.4) = 57.11% Formation (Km.) : (Scope= 26.282/Physical progress= 1.6) = 6.09% Land Acquisition (Hect.) : (Scope= 167.945/Physical progress= 167.945) = 100%

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone