Land Acquisition (Hect.) : (Scope= 172.31/Physical progress= 168.47) = 97.77%
Earth Work (Lakh Cum.) : (Scope= 21/Physical progress= 18.71) = 89.04%
Formation (Km.) : (Scope= 26.282/Physical progress= 9) = 34.24% (In seven Km, i.e. upto Sile final surfacing is balance)
Minor Bridge (Nos.) : (Scope= 55/Physical progress= 25) = 65%
RUB (Nos.) : (Scope= 13/Physical progress= 7) = 68%
Major Bridge(Nos.) : (Scope= 27/Physical progress= 9) = 60% | Land Acquisition (Hect.) : (Scope= 172.31/Physical progress= 167.945) = 97.47%
Earth Work (Lakh Cum.) : (Scope= 18.21/Physical progress= 10.4) = 57.11%
Formation (Km.) : (Scope= 26.282/Physical progress= 1.6) = 6.09% |