Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 201.92
|
Time Overrun (Months)-
68
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Land Acquisition (Hect.) : (Scope= 172.31/Physical progress= 168.47) = 97.77%
Earth Work (Lakh Cum.) : (Scope= 21/Physical progress= 15.30) = 72.85%
Formation (Km.) : (Scope= 26.282/Physical progress= 3.80) = 15.00%
Minor Bridge (Nos.) : (Scope= 55/Physical progress= 14) = 42%
RUB (Nos.) : (Scope= 13/Physical progress= 5) = 55.56%
Major Bridge(Nos.) : (Scope= 27/Physical progress= 4) = 36%
| Land Acquisition (Hect.) : (Scope= 172.31/Physical progress= 167.945) = 97.47%
Earth Work (Lakh Cum.) : (Scope= 18.21/Physical progress= 10.4) = 57.11%
Formation (Km.) : (Scope= 26.282/Physical progress= 1.6) = 6.09%
|
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |