Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : MULTI MODAL TRANSPORT SYSTEM(MMTS) PHASE-II HYDERABAD.

Reported Date : 25-APR-24

Monthly Report : 4 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
632.6801169.23

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
668.480426.051094.53

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20160/03/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5050

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

This Project is fully completed and commissioned on 07-02-2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks