Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : PIRPAINTI-JASIDIH.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   133.39

Time Overrun (Months)-    72

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
915.9802137.81

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
728.0355.151.48784.66

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20223/20283/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
151.50

Ministry Review Date

LatestLastPhysical Progress (%)Status
45Ongoing

Monthly Status

Background Information

Mohanpur - Hansdiha (39.71 Km) part of Pirpainti - Jasidih (99.73 Km) project: Completed & Commissioned on 31.03.2023. Balance section: Godda - Pirpainti (60.24 Km): Project sanctioned on Railway cost in Dec22 due to Jharkhand State disassocited themselves for funding. Land Acquition: Against 418.82 Acre of Pvt Land and 51.934 Acre of Govt land in Godda – Mahagama Section, Rs. 238.60 Cr & Rs. 46.65 Cr respectively has been deposited to Jharkhand State so far.The GODDA - PIRPAINTI Section has been declared as SPECIAL RAILWAY PROJECT vide Gazette Notification dated 17.03.2023 (Sectoin 2 of the Railway (Amendment Act-2008). DC/Godda/Jharkhand have been requested accordingly for early appointment of CALA vide letter No. CAO/Con/L/268(A) dated 29.03.23. Early appointment is solicited to expedite the prpgress. Hasdiha – Mohanpur (39.71 km) -- Section: Hansdiha – Harlatarn (23.73 Km) – Commissioned on 31.03.2023. Harlatarn – Mohanpur (15.98 Km) – Commissioned on 22.03.2023.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone