Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : PIRPAINTI-JASIDIH.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   185.03

Time Overrun (Months)-    72

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
915.9802610.84

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
784.6672.74263.711121.11

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20223/20283/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3350

Ministry Review Date

LatestLastPhysical Progress (%)Status
45Ongoing

Monthly Status

Background Information

An amount of Rs.259.60 Cr for 20.86 Ha Govt Land deposited to State on 24.03.2025.Mohanpur - Hansdiha (39.71 Km) part of Pirpainti - Jasidih (99.73 Km) project: Completed & Commissioned on 31.03.2023. Balance section: Godda - Pirpainti (60.24 Km): Project sanctioned on Railway cost in Dec22 due to Jharkhand State disassocited themselves for funding. Land Acquition: Against 418.82 Acre of Pvt Land and 51.934 Acre of Govt land in Godda – Mahagama Section, Rs. 238.60 Cr & Rs. 46.65 Cr respectively has been deposited to Jharkhand State so far.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone