Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : PLASSEY-JIAGANJ DOUBLING.

Reported Date : 14-JAN-19

Monthly Report : 11 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
248.070234.41

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
252.8110.13.34266.25

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20150/011/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
50

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Section commissioned on 27.01.2017.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks