Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : BANDEL-BOINCHI 3RD LINE.

Reported Date : 28-JUN-23

Monthly Report : 6 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
288.350402.48

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
568.832.972.15603.92

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/09/20215/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
7.250

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Work sanctioned by Board for Rs. 288.35 Crs vide letter No. 2010/W-2/ER /DL/14/pt. I dt. 31.05.2011. Detailed estimate sanctioned for Rs. 238.36 Crs. Section Boinchi – Magra ( 23.54 KM ) 3rd line – Completed and commissioned on 02.09.2020. In remaining section i.e Bandel – Magra (6.99 Km ) – Commissioned on 30.05.2022.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

   <