Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : PIRPAINTI-BHAGALPUR.

Reported Date : 07-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
261.380565

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
548.853.671.07553.59

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/05/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
100

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Section Pirpainti – Bhagalpur ( 50.06 KM ) doubling – Commissioned on 14.05.2019

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks