Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : DANKUNI-CHANDANPUR 4TH LINE, 1ST PHASE OF DANKUNI-SHAKTIGARH 4TH LINE WITH MM BARUIPARA FURFURA NL.

Reported Date : 07-NOV-23

Monthly Report : 10 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
365.170335.5

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
654.9625.795.96686.71

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20170/012/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
60.950

Ministry Review Date

LatestLastPhysical Progress (%)Status
67Completed

Monthly Status

Background Information

(i) Dankuni – Baruipara ( 11.28 Km ) 4th line – CRS inspection conducted on 28.12.2019 and authorization received at 100 KMPH. Section commissioned on 10.08.2020. (ii) Baruipara – Chandanpur 4th line (14.13 Km)– Commissioned on 02.12.2022. MM for Baruipara – Furfura (12.30 Km) New line –Sanctioned for Rs. 97.56 Cr. Work could not be started due to non- availability of land. However, the work has been kept in abeyance by Railway Board vide letter 2018/W- II/ER/Misc/12, dated 02.11.2018 having no tangible benefit.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks