Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : WARDHA-NANDED MAHARASHTRA.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   8.75

Time Overrun (Months)-    45

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3168.2903445.48

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1647.31342.74159.522149.57

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20230/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
8500

Ministry Review Date

LatestLastPhysical Progress (%)Status
47Ongoing

Monthly Status

Background Information

Wardha to Yavatmal (78km) Project sanctioned on 60:40 cost sharing with Govt. of Maharashtra. Wardha to Yavatmal is being executed by C.Rly. Yavatmal to Nanded (206 km) is transferred to RVNL. Complete land acquisition done except Additional land required by RVNL, which is being acquired under Railway (Amendment) Act 2008. Wardha - Deoli Section (15 kms) commissioned on 30.08.2023 and Deoli-Kalamb (23.61 Km) commissioned on 23.12.2023. Balance work is in progress.Wardha to Yavatmal (78km) Project sanctioned on 60:40 cost sharing with Govt. of Maharashtra. Wardha to Yavatmal is being executed by C.Rly. Yavatmal to Nanded (206 km) is transferred to RVNL vide Boards letter No.2004/W-I/RVNL/13Pt.I dt.15.11.2018. For complete project, Out of Total 2117.084 Ha land in complete Wardha- Nanded section, land acquired is 1911.243 Ha and Balance land to be be acquired =205.841 Ha.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone