Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : WARDHA-NANDED MAHARASHTRA.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3445.4803445.34

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2990.05131.2135.213156.47

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20270/01/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
206.98835

Ministry Review Date

LatestLastPhysical Progress (%)Status
47Ongoing

Monthly Status

Background Information

1. Earthwork (Cutting + Filling) = 22,000 cum 2. Side Drain = 3 KM 3. Tunnel Excavation = 20,000 cum 4. Minor Bridge - 799/1 {Completed}Wardha to Yavatmal (78km) Project sanctioned on 60:40 cost sharing with Govt. of Maharashtra. Wardha to Yavatmal is being executed by C.Rly. Yavatmal to Nanded (206 km) is transferred to RVNL. Complete land acquisition done except Additional land required by RVNL, which is being acquired under Railway (Amendment) Act 2008. Wardha - Deoli Section (15 kms) commissioned on 30.08.2023 and Deoli-Kalamb (23.61 Km) commissioned on 23.12.2023. Balance work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks