Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : KALYAN-KASARA 3RD LINE.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   80.68

Time Overrun (Months)-    69

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
792.8901432.61

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
679.4151.8431.13862.37

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20210/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
85160

Ministry Review Date

LatestLastPhysical Progress (%)Status
50Ongoing

Monthly Status

Background Information

The total land required is 49.2388 Ha. including 33.1127 Ha of private land, 4.8143 Ha of Govt land and 11.3118 Ha. of forest land. Land acquired till date is 36.3799 Ha (32.0528 Ha of private land and 4.3271 Ha of Govt land). Earthwork & Minor bridge construction in progress in ASO-KE section. Work of major bridges in progress in KYN-ASO section. For forest land clearance, MoEF advised State Govt. for providing CA land.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone