Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 80.68
|
Time Overrun (Months)-
69
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| The total land required is 49.2388 Ha. including 33.1127 Ha of private land, 4.8143 Ha of Govt land and 11.3118 Ha. of forest land. Land acquired till date is 36.3799 Ha (32.0528 Ha of private land and 4.3271 Ha of Govt land). Earthwork & Minor bridge construction in progress in ASO-KE section. Work of major bridges in progress in KYN-ASO section. For forest land clearance, MoEF advised State Govt. for providing CA land. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |