Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : HANSDIHA-GODDA NL.

Reported Date : 07-OCT-21

Monthly Report : 9 / 2021

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
542.180663.13

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
536.898.53.55545.97

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/03/2021

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
820

Ministry Review Date

LatestLastPhysical Progress (%)Status
85Completed

Monthly Status

Background Information

As per Rly Board s letter No. 2006/W-2/ER/SY/NL/HG pt. Dt. 07.02.2011 project is on 50/50 cost sharing basis with Jharkhand Government. Revised estimate costing Rs. 663.13 Cr. sanctioned on 06.02.20. Share of cost of Jharkhand Govt. is Rs. 331.56 Crs. against the fund deposited Rs. 199.85 crs. So, balance fund to deposit against this work is Rs. 131.71 Crs. by Jharkhand Govt. State Govt is requested to deposit balance fund against their share of cost early. Hansdiha – Godda (32.0Km) : Entire project commissioned (i) Hansdiha – Poreyahat (15.50 Km) : Commissioned on 30.08.2019 (ii) Poreyahat – Godda (16.50 Km) : Commissioned on 05.03.2021

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks