Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : SAINTHIA-TARAPITH 3RD LINE.

Reported Date : 14-JAN-19

Monthly Report : 11 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
193.440186.64

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
252.8124.733.14280.68

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/011/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
180

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Gadhadharpur – Tarapith Road (14.10 km ) Commissioned on 19.04.2017. Sainthia – Gadhadharpur (7.19 km) all work completed and commissioned on 07.10.2018

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks