Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : BOINCHI-SHAKTIGARH 3RD LINE.

Reported Date : 28-JUN-23

Monthly Report : 6 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
175.80495.1

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
403.3948.32.6454.29

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/09/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
35.850

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Section: Boinchi – Rasulpur( 18.88 KM ) - Commissioned on 18.09.2019. Balance section Rasulpur - Shaktigarh (6.95Km) – Commissioned on 16.09.2022

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks