Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : LILUAH-DANKUNI 3RD LINE, MM FOR DANKUNI-JONGALPARA-FURFURA SHARIF NL.

Reported Date : 08-MAR-22

Monthly Report : 2 / 2022

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
257.420257.42

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
108.031.630109.66

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20140/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
10

Ministry Review Date

LatestLastPhysical Progress (%)Status
75Completed

Monthly Status

Background Information

3rd line work commissioned between Dankuni & Bally only, as it is not feasible to provide 3rd line between Bally &Liluah. Dankuni – Bally (6.15 km) is commissioned on 13.08.2018. Subsequently the material modification works were sanctioned :Dankuni – Jongalpara – Furfura Sharif (20 km) new line : The work sanctioned in year 2009-10 at a cost of Rs. 147.49 Cr. FLS completed. Work being executed by RVNL. 226.542 acres of land required to be acquired. Work could not be started due to non availability of land. However the work has been kept Frozen by Railway board, vide letter 2018/W- II/ER/Misc/12, dated 02.11.2018 having no tangible benefit.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks