Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : KATWA-PATULI DOUBLING WITH NEW MM FOR AHMEDPUR-KATWA GC.

Reported Date : 14-JAN-19

Monthly Report : 11 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
423.660479.03

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
614.5323.3314.93652.79

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20170/011/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
50

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Katwa – Patuli doubling – completed & commissioned on 30.11.2014. Subsequently material modification works were sanctioned :- Ahmedpur – Katwa – (GC) Commissioned on 30.12.2017.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

   <