Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : WARDHA-SEWAGRAM NGP 3RD LINE.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    47

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
540.020540.02

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
542.82132.0735.78710.67

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/02/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
125155

Ministry Review Date

LatestLastPhysical Progress (%)Status
72Ongoing

Monthly Status

Background Information

Sindi- Butibori (19.3km) 3rd commissioned in December 2019. Butibori-Khapri 3rd line (15.29km) commissioned on 14.05.2023. Khapri Ajni 9.24 km Completed. CRS inspection done & section commissioned on 16.03.24. CRS authorization received. Total Land acquisition has been completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone