Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : WARDHA-SEWAGRAM NGP 3RD LINE.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    36

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
540.020540.02

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
401.5245.9419.62467.08

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1500

Ministry Review Date

LatestLastPhysical Progress (%)Status
72Ongoing

Monthly Status

Background Information

Sindi- Butibori (19.3km) 3rd commissioned in December 2019. Butibori-Khapri 3rd line (15.29km) commissioned on 14.05.2023. Khapri Ajni 9.24 km Completed. CRS inspection done & section commissioned on 16.03.24. CRS authorization received. Total Land acquisition has been completed.Sindi- Butibori (19.3km) 3rd line completed & commissioned in December 2019. Total Land acquisition has been completed. Balance section work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone