Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH WESTERN RAILWAY.
Project Name : BAGALKOT-KUDACHI NL.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   39.71

Time Overrun (Months)-    132

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
986.313781378

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
458.12143.59.01601.72

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20160/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
150220

Ministry Review Date

LatestLastPhysical Progress (%)Status
24-JAN-2434Ongoing

Monthly Status

Background Information

i) In Khajjidhoni - Lokapur (7.3 Kms) section, commissioned for goods traffic on 10.09.2024, CRS inspection completed on 18.03.2025 and authorization received on 03.04.2025. ii) EPC tender was awarded for the section between Lokapur - Yadwad (23 Km) on 31.05.2023 and earthwork is in progress. iii) EPC tender for works between the section Yadwad - Jamkhandi (25 Km) was awarded on 04.06.2024 and work in progress in 7 Km stretch (In balance locations, farmers objecting to commence the works due to various issues). iv) EPC tender for the sections between Jamkhandi - Harugeri (37.6 Km) is planned to be called after completion of resurvey of land which is in progress between Km: 72/000 - 97/000 (Mudhol - Malapura, Shirol-1, Huliyala, Siddapura, Shirol -2, & Kallahalli villages). v) For the section between and Harugeri - Kudachi (19.7 Km), EPC tender is proposed to be called in Apr 25 pending acquisition of balance land by GoK. vi) For the financial year 2024-25, an amount of Rs. 250 Cr was requested from GoK vide letter No.W.63/CN/BNC/Bud/E8193 dated 19.03.2024. However, no amount has been deposited. vii) A meeting was conducted by GM/SWR with CS/IDD/GoK on 19.09.2024 to expedite the land acquisition of new line projects and other issues involved in the cost sharing projects. viii) Meeting was conducted with Railways under the chairmanship of Secretary IDD/GoK on 28.01.2025 & 30.01.2025 to discuss issues pertaining to this project.i) Khajjidhoni - Lokapur (9 Kms) - Work is under progress and is targeted for the financial year 2023-24 with ABS system. ii) EPC tender was awarded for the section between Lokapur - Yadwad (22 Km) on 31.05.2023 and planning work is in progress. iii) EPC tender for works between the section Yadwad - Jamkhandi (24.6 Km) was floated on 03.08.2023 and bid opened on 15.02.2024 and the entire land has been handed over in this section. iv) EPC tender for the section Jamkhandi - Jagdal (17 Km) was floated on 05.09.2023 with bid opening on 03.04.2024 and the entire land has been handed over in this section. v) EPC tender for the section Jagdal - Suttati (28.5 Km) was floated on 13.10.2023 with bid opening on 30.04.2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone