i) Bagalkot - Lokapur (37.3 Km) section commissioned
ii) Lokapur - Yadwad (23 Km) section earthwork is in progress.
iii) Yadwad - Jamkhandi (25 Km) work in progress in 7 Km stretch (In balance locations, farmers objecting to commence the works due to various issues).
iv) EPC tender for the sections between Jamkhandi - Harugeri (37.6 Km) is planned to be called after completion of resurvey of land which is in progress between Km: 72/000 - 97/000 (Mudhol - Malapura, Shirol-1, Huliyala, Siddapura, Shirol -2, & Kallahalli villages).
v) For the section between and Harugeri - Kudachi (19.7 Km), EPC tender is proposed to be called in Aug 25 pending acquisition of balance land by GoK.
vi) A meeting was conducted by GM/SWR with CS/IDD/GoK on 19.09.2024 to expedite the land acquisition of new line projects and other issues involved in the cost sharing projects.
vii) Meeting was conducted with Railways under the chairmanship of Secretary IDD/GoK on 28.01.2025 & 30.01.2025 to discuss issues pertaining to this project.
viii) Meeting was conducted by Secretary, IDD with railways on 02.06.2025 and discuss regarding assets compensation payment pending for the project. | i) Khajjidhoni - Lokapur (9 Kms) - Work is under progress and is targeted for the financial year 2023-24 with ABS system.
ii) EPC tender was awarded for the section between Lokapur - Yadwad (22 Km) on 31.05.2023 and planning work is in progress.
iii) EPC tender for works between the section Yadwad - Jamkhandi (24.6 Km) was floated on 03.08.2023 and bid opened on 15.02.2024 and the entire land has been handed over in this section.
iv) EPC tender for the section Jamkhandi - Jagdal (17 Km) was floated on 05.09.2023 with bid opening on 03.04.2024 and the entire land has been handed over in this section.
v) EPC tender for the section Jagdal - Suttati (28.5 Km) was floated on 13.10.2023 with bid opening on 30.04.2024. |