Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH CENTRAL RAILWAY.
Project Name : KAZIPET-VIJAYAWADA 3RD LINE WITH ELECTRIFICATION.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   5.16

Time Overrun (Months)-    24

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1856.9501952.68

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1144.19468.8601613.05

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20230/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

DE sanctioned between KI&BZA (17.49 Km) at a cost of 163.50 Crs. in Aug 2014. Detailed estimate for KAZIPET-KONDAPALLI (202 km) sanctioned by Railway Board for Rs.1693.45 Cr Dt. 02.02.2017. 2.LA is in progress. Warangal 36.376-31.334= 5.042 Ha (LA is in advance stage of acquisition award to be passed.) 2. Mahbubabad 31.117-24.938 = 6.179 , Khammam 59.17- 55.68 =3.48 4.Krishna 4.14-4.14 = 0 Total 128.71-111.02 = 17.69 3.Details of sections targeted for completion during 2023-24: Nekkonda – Chintalpalli Commissioned on 26.06.23 North West Block Hut – Vijayawada Dec-23 Chintalapalli – Warangal Dec-23 Pandilapalli-Bonakalu :Mar-24 Bonakalu-Motumari : Mar-24 Erupalem – Madhira : Mar-24 "Hasanparthi-Kazipet-Warangal (incl KZJ-WL Byepass)" : May-23 Motumari- Madhira : Jan-24 . Total 68.09 Km commissioned. Balance – 151.542 Km Total 68.09 Km commissioned. Balance – 151.542 Km. Pandilapalli-Bonakallu (19.00Km): Track linking for 18.00 Km has been completed. : CRS authorization received on 18.03.2024 for a length of 20.88 Km. Warangal – Chintalpalli:CRS authorization received on 21.12.2023 for a length of 12.218Km. PCEE authorizations received on 20.12.2023. Tripling commissioned on 21.12.2023 at 90 Kmph sectional speed. Pandilapalli – Bonakalu (19.00 Km) : CRS authorization received on 18.03.2024 for a length of 20.88 Km."Kondapalli-Vijayawada Part DE sanctioned between KI&BZA (17.49 Km) at a cost of 163.50 Crs. in Aug 2014. Between BZA-KI: Works completed bet KI- NWBH cabin. 11.8 Km of track linking completed. Rayanapadu Yard: Laying of New Common loop line completed duly dismantling the existing 2 goods lines in connection with tripling work. Vijayawada A (NWBH)?Kondapalli (9.08Km), New West Block Hut-Vijayawada (7.6Km) are targeted in 2022-23. Detailed estimate for KAZIPET-KONDAPALLI (202 km) sanctioned by Railway Board for Rs.1693.45 Cr Dt. 02.02.2017. LA is in progress. Kazipet yard: a) Goods stabling line formation for 8, 9, 10 & 11 lines completed, Track linking work is in progress. b)Two nos newly constructed Pit Line No 1 & 2 (lengths 674 m each) of 26 Coach capacity as per CAMTECH Drawing at Kazipet Junction were inaugurated by GM on 24.12.2021. With this now Full rake Train (26 Coach) maintenance can be done at Kazipet. c) RRI cabin ground level slab, 1st &2nd floor slab completed. Electrical works in progress. OHE building ground floor and 1st floor slab & Brick work completed. Plastering, brightening and flooring works are in progress. Tower car shed completed. Kazipet-Warangal: 16 out of 22 minor bridges completed. Formation up to SQ2 level completed for 4 Km. Details of sections targeted for completion during 2022-23: 1. Vijayawada A (NWBH) ?Kondapalli 12.49 Km: CRS authorization received on 20.09.22 for a speed of 75 Kmph. 2. Kondapalli ?Cheruvumadhavaram 7.87 Km: CRS authorization received on 20.09.22 for a speed of 90 Kmph. ( Excluding CVV Yard ) 3. Cheruvumadhavaram ?Errupalem 16.50 Km: 14.2 Km of track linking completed. , Eerrupalem Foot Over Bridge (FOB) completed 4. Nekkonda - Chintalpalli 17.20Km: 1.00Km Track linking completed. 5. NWBH-Vijaywada (7.60 Km): 0.5 Km of track linking has been done so far. 6. In Nekkonda-Dornakal 54 Km, Dornakal-Yerrupalem (84 Km) Tender schedule under preparation. Br No 501 & 727 completed Br No 620 Sub str completed, Super str launching in progress "

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

   <