Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH CENTRAL RAILWAY.
Project Name : KAZIPET-VIJAYAWADA 3RD LINE WITH ELECTRIFICATION.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   5.16

Time Overrun (Months)-    24

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1856.9501952.68

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1144.19457.386.931688.42

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20230/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

Total 137.799 Km commissioned. Balance – 81.84 Km. Nekkonda – Chintalpalli Commissioned on 26.06.23 North West Block Hut – Kondapalli- Commissioned on 20.09.2022, Chintalapalli – Warangal Commissioned on 21.12.23, Pandilapalli-Bonakallu (19.00Km): CRS authorization received on 18.03.2024 for a length of 20.88 Km. Warangal – Chintalpalli: CRS authorization received on 21.12.2023 for a length of 12.218Km. PCEE authorizations received on 20.12.2023. Pandilapalli – Bonakalu (19.00 Km) : CRS authorization received on 18.03.2024 for a length of 20.88 Km.NWBH hut – Vijayawada(4.717) Commissioned on 7.10.24, Erupalem-Madhira(14.842) –commissioned on 27.08.24. Bonakalu-Motumari (10.91 Km) commissioned on 29.01.25. Pandilapalli-Khammam(9.39), commissioned on 24.03.25. Works are in progress in Motumari-Madhira(6.34), Nekonda-Mahabubabad(30.66), Khammam-Dornakal(23.09) & Dornakal-Mahabubad(24.25).DE sanctioned between KI&BZA (17.49 Km) at a cost of 163.50 Crs. in Aug 2014. Detailed estimate for KAZIPET-KONDAPALLI (202 km) sanctioned by Railway Board for Rs.1693.45 Cr Dt. 02.02.2017. 2.LA is in progress. Warangal 36.376-31.334= 5.042 Ha (LA is in advance stage of acquisition award to be passed.) 2. Mahbubabad 31.117-24.938 = 6.179 , Khammam 59.17- 55.68 =3.48 4.Krishna 4.14-4.14 = 0 Total 128.71-111.02 = 17.69 3.Details of sections targeted for completion during 2023-24: Nekkonda – Chintalpalli Commissioned on 26.06.23 North West Block Hut – Vijayawada Dec-23 Chintalapalli – Warangal Dec-23 Pandilapalli-Bonakalu :Mar-24 Bonakalu-Motumari : Mar-24 Erupalem – Madhira : Mar-24 "Hasanparthi-Kazipet-Warangal (incl KZJ-WL Byepass)" : May-23 Motumari- Madhira : Jan-24 . Total 68.09 Km commissioned. Balance – 151.542 Km Total 68.09 Km commissioned. Balance – 151.542 Km. Pandilapalli-Bonakallu (19.00Km): Track linking for 18.00 Km has been completed. : CRS authorization received on 18.03.2024 for a length of 20.88 Km. Warangal – Chintalpalli:CRS authorization received on 21.12.2023 for a length of 12.218Km. PCEE authorizations received on 20.12.2023. Tripling commissioned on 21.12.2023 at 90 Kmph sectional speed. Pandilapalli – Bonakalu (19.00 Km) : CRS authorization received on 18.03.2024 for a length of 20.88 Km.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks