Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : BHANUPALI-BILASPUR BERI NL.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
13370.2906753.42

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
5369.57005369.57

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20260/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

Work is in progress. Target for commissioning: March 2025.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks