Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : BHANUPALI-BILASPUR BERI NL.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   127.62

Time Overrun (Months)-    -21

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2966.9906753.42

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3486.22976.22481.894944.33

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20260/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
17001700

Ministry Review Date

LatestLastPhysical Progress (%)Status
49Ongoing

Monthly Status

Background Information

Work is in progress. Target for commissioning: March 2025.Work being executed by RVNL and work is in progress in 0 to 20 km stretch. Land acquisition is in progress from km 20 to km 63.1. Target for commissioning: March 2025.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone