Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH WESTERN RAILWAY.
Project Name : RAYADURGA-TUMKUR NL.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   16.57

Time Overrun (Months)-    24336

Total/Pending/Completed Milestone - 2 / 0 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2062.32404.032404.03

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1098.72124.716.51239.92

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/012/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
121193.42

Ministry Review Date

LatestLastPhysical Progress (%)Status
24-JAN-2460Ongoing

Monthly Status

Background Information

i) Tender for the sections between Tumkur - Urukere (12 Km) and Pavagada - Dodahalli (16 Km) has been awarded during Aug 2023 and the planning is in progress. ii) For the remaining sections, EPC tenders will be called after acquiring 90% of land by Government of Karnataka. iii) GM/SWR vide letter No.W.193/CN/BNC/IDD/General dt 05.10.2023 has requested to direct all the concerned to expedite the land acquisition for all the new lines and hand over the same at the earliest.(i)GoK has intimated their willingness to partially share a cost share a cost of Rs. 520.54 Cr against heir share against their share of Rs 726.27 Cr vide DO.No.IDD 192 NSW 2022 (part-1) dtd.15.11.2022 and eference has been made to railway board to communicate the decision regarding the same. (ii) Railway Board has agreed the proposal for funding the net shortfall of Rs.205.63 Cr by ministry of ailways. (iii) Subsequently GoK has accorded the administrative approval for sharing the revised cost of Rs.520.54 r by issuing G.O. on 16.03.2023. (iv) GM/SWR has requested Railway Board vide letter No. W.193/CN/BNC/TK-RDG/NL dtd 24.01.2023 to accord anction to fund the additional cost falling in Andhra Pradesh. (v Govt. of Andhra Pradesh vide letter Dt 13/06/2023 has requested to examine the preliminary report submitted by the Collector/Ananthapuram so as to reduce the land acquisition involved in the project and the completion period of the project. Accordingly SWR has decided to consider the proposal as suggested by GoAP.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone