Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH WESTERN RAILWAY.
Project Name : RAYADURGA-TUMKUR NL.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 2 / 0 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2495.592495.862495.86

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1629.5824.2721.491675.34

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
9/20150/02/2028

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
609.10

Ministry Review Date

LatestLastPhysical Progress (%)Status
06-MAR-2465Ongoing

Monthly Status

Background Information

"i) Work is under progress for the section between Tumkur - Urukere (11 Km), Pavagada - Doddahalli (16 Km) & Madakasira - Pavagada (22 Km) ii) EPC tender for the balance sections between Koratagere - Madhugiri (21 km) & Madhugiri - Madakasira (35 Km) awarded on 21.05.2025 & 13.05.2025. iii) EPC tender for Urukere - Koratagere (18 Km) was dropped on 09.05.2025 due to non-submission of PG and fresh tender will be invited by July 2025. iv) A meeting was conducted by GM/SWR with CS/IDD/GoK on 19.09.2024 to expedite the land acquisition of new line projects and other issues involved in the cost sharing projects. v) Meeting was conducted with Railways under the chairmanship of Secretary IDD/GoK on 30.01.2025 with all concerned DCs. vi) Based on the MoM of Pragathi Review meeting, Chief Secretary, GoK has requested to provide a detailed cost breakup of the revised project estimate. Accordingly, the current anticipated cost was submitted to GoK vide etter dated 03.06.2025 to issue the in-principle approval for the project."i) Tender for the sections between Tumkur - Urukere (12 Km) and Pavagada - Dodahalli (16 Km) has been awarded during Aug 2023 and the planning is in progress. ii) For the remaining sections, EPC tenders will be called after acquiring 90% of land by Government of Karnataka. iii) GM/SWR vide letter No.W.193/CN/BNC/IDD/General dt 05.10.2023 has requested to direct all the concerned to expedite the land acquisition for all the new lines and hand over the same at the earliest.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks