Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTHERN RAILWAY.
Project Name : ANAND VIHAR-TILAK BRIDGE 3RD AND 4TH LINE.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
586.360699

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
169.9904.23174.22

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20230/06/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
107.33120.06

Ministry Review Date

LatestLastPhysical Progress (%)Status
45Ongoing

Monthly Status

Background Information

Progress of month May’25 : Work on well foundations (4 nos. out of 7 nos.) of Yamuna Bridge is going on.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks