Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTHERN RAILWAY.
Project Name : AMBALA CANTT-DHAPPER PH-1 WITH NEW MM OF DHAPPER-CHANDIGARH.

Reported Date : 13-AUG-19

Monthly Report : 6 / 2019

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
338.54338.54390

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
380.762.87.98384.61

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/04/20186/2019

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
18-JUL-19100Completed

Monthly Status

Background Information

((A) Phase-I from UMB to DHPR section opened for traffic on 05-10-15 & handed over to O/L (B) MM for DL of DHPR to CDG amounting to Rs.199 cr sanctioned by Rly Bd on 02-01-13. (C) Phase-II from DHPR to CDG completed and commissioned after CRS inspection on 21.03.2018. Balance works of LHS in lieu of LC-117 and goods PF at Ghaggar station are in progress.Electrical work of goods PF will be done after completion of civil work.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks