Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : HOSPET-HUBLI-LONDA-VASCODAGAMA DL.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   73.61

Time Overrun (Months)-    45

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
212703692.6

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3055.13295.8748.773399.77

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20230/012/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
400400

Ministry Review Date

LatestLastPhysical Progress (%)Status
86Ongoing

Monthly Status

Background Information

270.62 km has been commissioned up to March 2024 out of total stretch of 352.28 km. Remaining 64.5 km work is in progress. Planning to commission the project in Dec 2026.1.269.04 km has been commissioned up to March 2021 out of total stretch of 352.28 km. 2. For Tinaighat-Vasco Phase-II, proposals for diversion of 10.45 Ha in Karnataka and 138.39 Ha in Goa are under consideration of MoEF. Execution of work in Tinaighat-Kalem (45.17 km) can only be planned after receipt of MoEF clearance. One NGO M/s. The Goa Foundation has filed a PIL before Goa Bench of High Court and Central Empowered Committee. There is massive resistance from public representatives as well as local public against doubling in the state of Goa. 3. All works in the section between Chandergoa-Madgoan (8.94km) and Majorda-Vasco (16.96km) were stopped as per discussions held with State Govt. of Goa since 20th Nov 2020. 4. 6.017 ha of land is yet to be acquired. Competent Authority SDM/Vasco has kept on hold the hearing against representation received against land acquisition in view of public protests.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone