"i) Talkal - Kushtagi (56 Km) commissioned
ii) Shahpur - Wadi (47km) - Earthwork, Blanketing, and Minor Bridges works are in progress.
iii) Kushtagi - Jumlapur road (20 km) - Earthwork is in progress.
iv) Shorapur - Shahpur (23.4 Km) - Preliminary works are under progress.
v) EPC tender schedule is being prepared for the balance sections and is being planned to be called by end of Jun-25. 100% land has been handed over for the balance sections.
vi) A meeting was conducted by GM/SWR with CS/IDD/GoK on 19.09.2024 to expedite the land acquisition of new line projects and other issues involved in the cost sharing project.
vii) Meeting was conducted with Railways under the chairmanship of Secretary IDD/GoK on 30.01.2025 with all concerned DCs." | 1) Hanumapur - Linganbandi(10.7km) - Section commissioned with ABS system on 20.02.2024
2) Linganbandi - Kushtagi (10.3 Km) - Earthwork, Minor bridges, ROBs, RUBs and ballast supply works are in progress.
3) Shahpur - Wadi (47km) - Earthwork, Blanketing, and Minor Bridges works are in progress.
4) Kushtagi - Jumlapur road(20 km) - Land acquisition has been completed and EPC tender for the section has been opened in Jun, 2023. Preliminary works are in progress.
5) Land acquisition is in progress for the Jumlapur road- Kekkra section and EPC Tender will be called when 90% of land is acquired. Anticipated target of the project - June 2025.
The targets are subject to the availability of land and fund from GoK and Railway. |