Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EASTERN RAILWAYS.
Project Name : MONIGRAM- NIMTITA.

Reported Date : 25-APR-24

Monthly Report : 4 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
250.930259.23

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
572.24030.79603.03

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/02/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1120

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

COMPLETED & COMMISSIONED ON 05.03.2024. DEDICATED TO THE NATION BY HON’BLE PRIME MINISTER ON 9TH MARCH, 2024 AT SILIGURI (WB).

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks