Sector Name : RAILWAYS.
Agency Name : SOUTH WESTERN RAILWAY.
Project Name : MARIKUPPAM - KUPPAM.

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
279.54296.72296.72

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
120.58.540121.12

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20160/012/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
81.20

Ministry Review Date

LatestLastPhysical Progress (%)Status
14Ongoing

Monthly Status

Background Information

"i) EPC tender awarded for 0 to 5.7 Km on 05.05.2023 and work is in progress and is targeted to be commissioned by Nov-2025. ii) EPC tender for balance 18 kms (km 5.7 to km 23.7) is being floated."(i) Status of Land in Karnataka - Km 1.0 to KM 4.7 belongs to Bharath Gold Mines Limited (BGML). BGML has given permission for execution of work in their land. (ii) RTC is issued by AC/Kolar in the name of Railways and accordingly DC has permitted to take up the work. (iii) Status of Land in Andhra Pradesh - Land acquisition is under process with DC/Chittoor, Andhra Pradesh for 250.28 acres. (iv) EPC tender awarded for 0 to 5.7 Km on 05.05.2023 and work is in progress (v) EPC tender was canceled on 12.01.2024 for balance 18 kms ( km 5.7 to km 23.7) as land could not be handed over by Govt of Andhra Pradesh and same is under preparation.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks