Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : VIJAYWADA-GUDUGOLANU-BHIMAVARAM-NARSAPUR DL (221 KM).

Reported Date : 28-JUN-23

Monthly Report : 6 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1503.7103633.12

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
4464.3619.4104483.77

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20206/20226/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
700700

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks