Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : BHADRAK - NERGUNDI 3RD LINE.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   52.35

Time Overrun (Months)-    60

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
843.041284.391284.39

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
957.9242.6736.651237.22

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
10/202010/202510/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
330274.34

Ministry Review Date

LatestLastPhysical Progress (%)Status
75Ongoing

Monthly Status

Background Information

i)This project is categorised as Critical project by Railway Board. (ii)Kapilas Rd-Salegaon DL(4.3 km)- Commissioned in May 2019. (iii)Kapilas Rd-Nergundi(4.2 km)commissioned in OCT-2022 (iv) Ranital Jn - Bhadrak-Commissioned-12/2024 (v) Baitarani Rd - Jajpur Keonjhar Rd (11.60kms)--completed, to be commissioned in 04/2025 (vi) Jajpur Keonjhar Rd-Jakhapura (7.90kms)TDC-05/2025. (vii) Kapilas Rd-Byree (10.10kms)-TDC-06/2025. (viii) Bhadrak - Baitarani Rd(31.90kms)- TDC-10/2025 (ix)The project has been taken out of EPC for execution through conventional mode of tendering, tenders for civil engg. works finalized. (vi)Over all TDC- Oct-2025.""""(i)This project is categorised as Critical project by Railway Board. (ii)Kapilas Rd-Salegaon DL(4.3 km)- Commissioned in May 2019. (iii)Kapilas Rd-Nergundi(4.2 km)commissioned in OCT-2022 (iv)JJKR-JKPR(7.90kms)& RLJC-BHC(5.0kms)-TDC-07/2024. (v) BTV-JJKR (11.60kms)---TDC-09/2024 (vi) BHC-BTV (31.90kms)--- TDC-12/2024 (vii) Kapilas Rd-Byree (10.10kms)-TDC-02/2025. (v)The project has been taken out of EPC for execution through conventional mode of tendering, tenders for civil engg. works finalized. (vi)Over all TDC-Feb-2025."""

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone