"(i)This project is categorised as Critical project by Railway Board.
(ii)Kapilas Rd-Salegaon DL(4.3 km)- Commissioned in May 2019.
(iii)Kapilas Rd-Nergundi(4.2 km)commissioned in OCT-2022
(iv)JJKR-JKPR(7.90kms)& RLJC-BHC(5.0kms)-TDC-07/2024.
(v) BTV-JJKR (11.60kms)---TDC-09/2024
(vi) BHC-BTV (31.90kms)--- TDC-12/2024
(vii) Kapilas Rd-Byree (10.10kms)-TDC-02/2025.
(v)The project has been taken out of EPC for execution through conventional mode of tendering, tenders for civil engg. works finalized.
(vi)Over all TDC-Feb-2025.""" | "(i)This project is categorised as Critical project by Railway Board.
(ii)Kapilas Rd-Salegaon DL(4.3 km)- Commissioned in May 2019.
(iii)Kapilas Rd-Nergundi(4.2 km)Works Completed and waiting for CRS inspection.-TDC-OCT-2022
(iv)Kapilas Rd-Byree(10.5 km)-TDC-Dec 2023.
(v)The project has been taken out of EPC for execution through conventional mode of tendering, tenders for civil engg. works finalized.
(vi)Over all TDC-March-24.""" |