i)This project is categorised as Critical project by Railway Board.
(ii)Kapilas Rd-Salegaon DL(4.3 km)- Commissioned in May 2019.
(iii)Kapilas Rd-Nergundi(4.2 km)commissioned in OCT-2022 and Haridaspur-Byree (16.80kms) commissioned in Sept-2023
(iv) Ranital Jn - Bhadrak (5.05km) commissioned in Dec-2024
(v) Jajpur Keonjhar Rd - Jakhapura (7.90kms)TDC-06/2025.
(v) Baitarani Rd - Jajpur Keonjhar Rd (11.60kms)--TDC-06/2025
(vi) Bhadrak - Baitarani Rd(31.90kms)- TDC-06/2026
(vii) Kapilas Rd-Byree (10.10kms)-TDC-01/2026.
(v)The project has been taken out of EPC for execution through conventional mode of tendering, tenders for civil engg. works finalized.
(vi)Over all TDC- JUNE-2026." | "(i)This project is categorised as Critical project by Railway Board.
(ii)Kapilas Rd-Salegaon DL(4.3 km)- Commissioned in May 2019.
(iii)Kapilas Rd-Nergundi(4.2 km)commissioned in OCT-2022
(iv)JJKR-JKPR(7.90kms)& RLJC-BHC(5.0kms)-TDC-07/2024.
(v) BTV-JJKR (11.60kms)---TDC-09/2024
(vi) BHC-BTV (31.90kms)--- TDC-12/2024
(vii) Kapilas Rd-Byree (10.10kms)-TDC-02/2025.
(v)The project has been taken out of EPC for execution through conventional mode of tendering, tenders for civil engg. works finalized.
(vi)Over all TDC-Feb-2025.""" |