Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : JHARSUGUDA-RENGALI DOUBLING.

Reported Date : 17-APR-18

Monthly Report : 2 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2010230

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
243.23.030243.26

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/02/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
72.25

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks