Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : KIRANDUL - JAGDALPUR DOUBLING.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   24.14

Time Overrun (Months)-    48

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
116001440

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1058.66259.0450.931368.63

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/03/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
86.5Ongoing

Monthly Status

Background Information

1. 5 Minor bridges 1143, 1144, 1154, 1155 (KMLR-BHNS), 1204 (BHNS-BCHL) completed this month 2. 5000 Cum of hard rock cutting done in BHNS-BCHL section. 3. Station Building at Kamalur flooring completed."Kamlur- Kawargaon- Dabpal (21.074Km) doubling CRS inspection done on 07.09.22 and commissioned on 15.09.22. Two minor bridges (1116, 1247) in Dantewada ? Kamlur & Bacheli - Kirandul completed. 17000 Cum of earthwork in formation done. 2000 Cum of ballast supply done."

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone