Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : KIRANDUL - JAGDALPUR DOUBLING.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   33.89

Time Overrun (Months)-    48

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
116001553.11

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1368.63118.416.081503.11

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/03/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
94Ongoing

Monthly Status

Background Information

1. Minor bridge completed- 1 no. - Br. No. 1241 (BHNS-BCHL) 2. Earthwork in cutting- 18515 Cum (BHNS-BCHL) and 10615 Cum (KMLR-BHNS) 3. Concreting done in Cum- 561 Cum in BHNS-BCHL section and 1637 Cum in KMLR-BHNS section. 4. Hard rock cutting - 2500 Cum in KMLR-BHNS section. Highlight of the month: BCHL-KRDL section commissioned on 09.03.2025.1. 5 Minor bridges 1143, 1144, 1154, 1155 (KMLR-BHNS), 1204 (BHNS-BCHL) completed this month 2. 5000 Cum of hard rock cutting done in BHNS-BCHL section. 3. Station Building at Kamalur flooring completed.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone