Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : SAMBALPUR - ANGUL RLY. ELECTRIFICATION.

Reported Date : 08-MAR-22

Monthly Report : 2 / 2022

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
155.81238.03238.03

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
221.483.280224.76

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20203/20226/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
07

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Completed

Monthly Status

Background Information

OHE electrification work in the doubling section from Jujumura to Maneswar is under progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks