Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST COAST RAILWAY.
Project Name : DELANG-PURI DOUBLING.

Reported Date : 03-JUL-18

Monthly Report : 4 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
165.160234.71

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
226.3500226.35

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20157/20157/2015

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
.450

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks