Sector Name : RAILWAYS.
Agency Name : RAIL VIKAS NIGAM LTD..
Project Name : THANJAVUR - PONMALAI DOUBLING (46.96 KM) WITH BYE-PASS LINE BEFORE PONMALAI (1.13 KM).

Reported Date : 05-JUL-18

Monthly Report : 4 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
190.10350

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
320.4100320.41

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/03/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
1065.33

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Project fully completed and commissioned in March 2018

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks