Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH WESTERN RAILWAY.
Project Name : HOSADURGA - CHICKJAJUR (28.89 KM).

Reported Date : 07-DEC-17

Monthly Report : 10 / 2017

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
203.4203.4273.84

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
274.726.31.67282.69

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/010/2017

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
46.99

Ministry Review Date

LatestLastPhysical Progress (%)Status
18-AUG-17100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks