Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : PHULERA - DIGANA DOUBLING.

Reported Date : 06-NOV-24

Monthly Report : 10 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
6000701.81

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
691.0774.470765.54

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20204/20244/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
400

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Phase wise commissioning of project :- (i)Degana- Borawar (39.936 Km):- CRS inspection has been done on 26.10.2021 & 27.10.2021 & CRS has authorized the opening of section for the public carriage of passengers at a maximum permissible speed of 95 Kmph. (ii) Borawar- Kuchaman city (19.836 Km):- CRS inspection has been done on 15.03.2022 & CRS has authorized the opening of section for the public carriage of passengers at a maximum permissible speed of 70 Kmph. (iii)Phulera - Govindi Marwar (26.50 Km) :- section commissioned on 27.12.2023. (iv) Kuchaman city - Nawa city(16 Km) :- section commissioned on 21.02.2024. (v)Nawa city - Govindi Marwar(8 Km) :- Planned for commissioning by April-2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks