Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH WESTERN RAILWAY.
Project Name : PHULERA - DIGANA DOUBLING.

Reported Date : 08-MAR-21

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 4 / 2021

Cost Overrun (%)-   16.97

Time Overrun (Months)-    31

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
6000701.81

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
111.31110.1614.66236.13

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/010/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
103149.5

Ministry Review Date

LatestLastPhysical Progress (%)Status
50Ongoing

Monthly Status

Background Information

•Earthwork done during the month –Nil , cumulative progress – 10,61,500 cum out of total 18,29,000 cum. •Blanketing done during the month -Nil, cumulative progress- 49,000 cum, out of 1,95,000 cum. •Major bridges completed during the month – Nil , cumulative progress – 1 out of total 14. •Minor bridges completed during the month – Nil , cumulative progress – 27 out of total 66. •Ballast supply during the month - 2,000 cum,cumulative progress- 1,80,000 cum, out of 3,17,000 cum. •Track linking completed during the month – 1.7 km , cumulative progress – 26.3 km out of total 108 km. •Earthwork cumulative progress – 10,61,500 cum out of total 18,29,000 cum. •Blanketing cumulative progress- 49,000 cum, out of 1,95,000 cum. •Minor bridges– 33 out of total 72. •Ballast supply during the month - 3,000 cum,cumulative progress- 1,15,000 cum, out of 2,99,000 cum.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone