Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : SAMASTIPUR-DARBANGHA.

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
519.33519.33519.33

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
626.16.5513.97640.68

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20250/010/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
600

Ministry Review Date

LatestLastPhysical Progress (%)Status
80Ongoing

Monthly Status

Background Information

a) Samastipur - Kishanpur (10 Km) - Commissioned on 24.07.2019 and handed over to Open line. b) Darbhanga - Thalwara (9.0 km) - Commissioned on 30.06.2020 and handed over to Open line on 29.10.2020. c) Kishanpur - Thalwara (12 km) (Permanent Diversion) - Commissioned on 24.08.2022 & section handed over to Open Line on 19.10.22. d) Kishanpur – Rambhadrapur (6 km) (Doubling) - Commissioned on 25.07.2023 & handed over to open line on 05.09.23 e) Rambhadrapur - Thalwara (12.0 km) (Doubling) - E/W & Blanketing - Work in Progress, Minor Br.- completed, Major br. - Work in progress, Construction of S&T Buildings -Completed, Track Linking - work in Progress, OHE work - In progress. Target of commissioning Oct’ 25.a) Samastipur - Kishanpur (10 Km) - Commissioned on 24.07.2019 and handed over to Open line. b) Darbhanga - Thalwara (9.0 km) - Commissioned on 28.06.2020 c) Kishanpur - Thalwara (12 km) (Permanent Diversion) - Commissioned on 24.08.2022 d) Kishanpur – Rambhadrapur (6 km) (Doubling)- Commissioned on 25.07.2023. e) Rambhadrapur - Thalwara (12.0 km) (Doubling) - E/W & Blanketing - Work in Progress, Minor Br.- 5 completed out of 5 no , Major br. - Br. no.15 Substructure work completed. At Br. No. 14, 15A & 17- work in progress, Track Linking - work in Progress, OHE work- In progress. Target of commissioning Mar’25.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

   <