a) Samastipur - Kishanpur (10 Km) - Commissioned on 24.07.2019 and handed over to Open line.
b) Darbhanga - Thalwara (9.0 km) - Commissioned on 30.06.2020 and handed over to Open line on 29.10.2020.
c) Kishanpur - Thalwara (12 km) (Permanent Diversion) - Commissioned on 24.08.2022 & section handed over to Open Line on 19.10.22.
d) Kishanpur – Rambhadrapur (6 km) (Doubling) - Commissioned on 25.07.2023 & handed over to open line on 05.09.23
e) Rambhadrapur - Thalwara (12.0 km) (Doubling) -
E/W & Blanketing - Work in Progress, Minor Br.- 5 nos completed out of 5 nos , Major br. - Work in progress, Track Linking - work in Progress, OHE work - In progress. Target of commissioning Oct’ 25. | a) Samastipur - Kishanpur (10 Km) - Commissioned on 24.07.2019 and handed over to Open line.
b) Darbhanga - Thalwara (9.0 km) - Commissioned on 28.06.2020
c) Kishanpur - Thalwara (12 km) (Permanent Diversion) - Commissioned on 24.08.2022
d) Kishanpur – Rambhadrapur (6 km) (Doubling)- Commissioned on 25.07.2023.
e) Rambhadrapur - Thalwara (12.0 km) (Doubling) -
E/W & Blanketing - Work in Progress, Minor Br.- 5 completed out of 5 no , Major br. - Br. no.15 Substructure work completed. At Br. No. 14, 15A & 17- work in progress, Track Linking - work in Progress, OHE work- In progress. Target of commissioning Mar’25. |