Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : SAMASTIPUR-DARBANGHA.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   36.67

Time Overrun (Months)-    24310

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
380519.33519.33

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
474.69140.4511.02626.16

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/010/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
80126.63

Ministry Review Date

LatestLastPhysical Progress (%)Status
70Ongoing

Monthly Status

Background Information

a) Samastipur - Kishanpur (10 Km) - Commissioned on 24.07.2019 and handed over to Open line. b) Darbhanga - Thalwara (9.0 km) - Commissioned on 30.06.2020 and handed over to Open line on 29.10.2020. c) Kishanpur - Thalwara (12 km) (Permanent Diversion) - Commissioned on 24.08.2022 & section handed over to Open Line on 19.10.22. d) Kishanpur – Rambhadrapur (6 km) (Doubling) - Commissioned on 25.07.2023 & handed over to open line on 05.09.23 e) Rambhadrapur - Thalwara (12.0 km) (Doubling) - E/W & Blanketing - Work in Progress, Minor Br.- 5 nos completed out of 5 nos , Major br. - Work in progress, Track Linking - work in Progress, OHE work - In progress. Target of commissioning Oct’ 25.a) Samastipur - Kishanpur (10 Km) - Commissioned on 24.07.2019 and handed over to Open line. b) Darbhanga - Thalwara (9.0 km) - Commissioned on 28.06.2020 c) Kishanpur - Thalwara (12 km) (Permanent Diversion) - Commissioned on 24.08.2022 d) Kishanpur – Rambhadrapur (6 km) (Doubling)- Commissioned on 25.07.2023. e) Rambhadrapur - Thalwara (12.0 km) (Doubling) - E/W & Blanketing - Work in Progress, Minor Br.- 5 completed out of 5 no , Major br. - Br. no.15 Substructure work completed. At Br. No. 14, 15A & 17- work in progress, Track Linking - work in Progress, OHE work- In progress. Target of commissioning Mar’25.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone

   <