Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH WESTERN RAILWAY.
Project Name : ARSIKERE-TUMKUR.

Reported Date : 06-JUL-22

Monthly Report : 6 / 2022

  

   

Total/Pending/Completed Milestone - 2 / 0 / 2

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
578749.69758.36

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
677.172.451.7681.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20202/20222/2022

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
51.80

Ministry Review Date

LatestLastPhysical Progress (%)Status
15-MAR-21100Completed

Monthly Status

Background Information

Entire project Arsikere - Tumkur (96 Km) was completed. Observations from Rly Board on MM estimate was received vide letter dt. 19-04-2022 was replied on 02-05-2022.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks