Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH WESTERN RAILWAY.
Project Name : HOTGI-KUDGI-GADAG.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   52.29

Time Overrun (Months)-    83

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1614.591877.812458.87

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2075.54401.6523.442500.63

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20190/02/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
170275

Ministry Review Date

LatestLastPhysical Progress (%)Status
89Ongoing

Monthly Status

Background Information

i) In Bagalkot - Mugalolli (8.4 Km) section, Major Bridges No. 33 & 36 works are in progress. ii) In Mugalolli - Jadramakunte (11.3 Km) section, speed trial run was completed on 27.06.2024. Engine rolling done in Feb 25. CRS planned along with Jadramkunte - Almatti section. iii) In Jadramkunte - Almatti (15.3 Km) section, engine rolling completed in Feb-25. iv) In Almatti - Wandal (9.6 Km) section, construction work of Important bridge 63D is in progress.1) Guledagudda - Bagalkot(13 Kms) section was commissioned on 28.12.2023. 2)In Bagalkot - Mugalolli (8.4 Km), Mugalolli - Jadramakunte (11.3 Km) and Jadramkunte - Almatti (15.3 Km) sections works are in progress 3) In Almatti - Wandal section, construction work of Important bridge 63D is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone