Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : SOUTH WESTERN RAILWAY.
Project Name : HOTGI-KUDGI-GADAG.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   36.26

Time Overrun (Months)-    69

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1614.591877.812200

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1845.27204.8425.432075.54

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20190/012/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
170227

Ministry Review Date

LatestLastPhysical Progress (%)Status
16-JAN-2388Ongoing

Monthly Status

Background Information

1) Guledagudda - Bagalkot(13 Kms) section was commissioned on 28.12.2023. 2)In Bagalkot - Mugalolli (8.4 Km), Mugalolli - Jadramakunte (11.3 Km) and Jadramkunte - Almatti (15.3 Km) sections works are in progress 3) In Almatti - Wandal section, construction work of Important bridge 63D is in progress.1)Guledagudda - Bagalkot(13 Kms) section is targeted for commissioning in December 2023, and works are under progress. 2)In Bagalkot - Mugalolli (8.4 Km) section, earthwork and blanketing works are in progress and the section is targeted for commissioning in Mar-2024. 3) In Mugalolli - Jadramakunte section (11.3 Km), works are in progress and the section is targeted for commissioning in Jan,2024. 4) In Jadramkunte - Almatti (15.3 Km) section, is targeted for commissioning in Feb, 2024. 5) In Almatti - Wandal section, construction work of Important bridge 63D is in progress and the section is targeted for commissioning in Dec-24.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone