Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EASTERN RAILWAY.
Project Name : GONDA GORAKHPUR LOOP WITH ANAND NAGAR NAUTANWA GC (260 KM).

Reported Date : 17-APR-18

Monthly Report : 2 / 2018

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
836.2601072.52

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1024.072.5801026.65

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/02/2018

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
.010

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

All sections are opened for traffic.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks