Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : DEDICATED FREIGHT CORRIDOR CORPORATION OF INDIA LTD.
Project Name : EASTERN DEDICATED FREIGHT CORRIDOR PROJECT.

Reported Date : 07-NOV-23

Monthly Report : 10 / 2023

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
11589051219

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
313040031304

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
0/00/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information


Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks