Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : NORTH EASTERN RAILWAY.
Project Name : ROSA-SITAPUR CANTT-BURHWAL DOUBLING.

Reported Date : 25-APR-24

Monthly Report : 4 / 2024

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1295.4202560

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2094.150168.422262.57

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/02/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
750

Ministry Review Date

LatestLastPhysical Progress (%)Status
100Completed

Monthly Status

Background Information

Commissioned on Feb-24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks