Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : KIUL - GAYA DOUBLING PROJECT.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   47.56

Time Overrun (Months)-    50

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1200.21200.21771.07

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1224.72274.1345.511544.36

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/05/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2000

Ministry Review Date

LatestLastPhysical Progress (%)Status
96Ongoing

Monthly Status

Background Information

Work allotted to IRCON vide Railway Board s letter no. 2015/W-1/Genl/ Presentation/Pt. dated 11.12.2015. Year wise target is as under: a) Manpur Jn - Wazerganj (20.34Km) - has been commissioned Dec 19 b) Wazerganj - Tilaiya Junction - has been commissioned Sep 22 c) Sheikhpura Junction - Kashi Chak (15.4 km) - has been commissioned on 01/09/2023 d) Luckeesarai Junction - Sheikhpura Junction - has been commissioned Feb 23 e) Kashi Chak - Warisale Ganj - has been commissioned Jan 24 f) Warisale Ganj - Nawadah - Targeted in April 24 g) Nawadah - Tilaiya Junction - Targeted in May 24Year wise target is as under: a) Manpur Jn - Wazerganj (20.34Km) - has been commissioned Dec19 b) Wazerganj - Tilaiya Junction - has been commissioned Sep22 c) Luckeesarai Junction - Sheikhpura Junction - has been commissioned Feb23 d) Sheikhpura Junction - Kashi Chak - Targeted in July23 e) Kashi Chak - Warisale Ganj - Targeted in Aug23 f) Warisale Ganj - Nawadah - Targeted in Dec23 g) Nawadah - Tilaiya Junction - Targeted in March24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone