Reported Date :
12-FEB-24
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2024
|
Cost Overrun (%)- 47.56
|
Time Overrun (Months)-
50
|
Total/Pending/Completed Milestone -
1
/
1
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
1224.72 | 274.13 | 45.51 | 1544.36 |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Work allotted to IRCON vide Railway Board s letter no. 2015/W-1/Genl/ Presentation/Pt. dated 11.12.2015. Year wise target is as under:
a) Manpur Jn - Wazerganj (20.34Km) - has been commissioned Dec 19
b) Wazerganj - Tilaiya Junction - has been commissioned Sep 22
c) Sheikhpura Junction - Kashi Chak (15.4 km) - has been commissioned on 01/09/2023
d) Luckeesarai Junction - Sheikhpura Junction - has been commissioned Feb 23
e) Kashi Chak - Warisale Ganj - has been commissioned Jan 24
f) Warisale Ganj - Nawadah - Targeted in April 24
g) Nawadah - Tilaiya Junction - Targeted in May 24 | Year wise target is as under:
a) Manpur Jn - Wazerganj (20.34Km) - has been commissioned Dec19
b) Wazerganj - Tilaiya Junction - has been commissioned Sep22
c) Luckeesarai Junction - Sheikhpura Junction - has been commissioned Feb23
d) Sheikhpura Junction - Kashi Chak - Targeted in July23
e) Kashi Chak - Warisale Ganj - Targeted in Aug23
f) Warisale Ganj - Nawadah - Targeted in Dec23
g) Nawadah - Tilaiya Junction - Targeted in March24 |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |