Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : KIUL - GAYA DOUBLING PROJECT.

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   47.56

Time Overrun (Months)-    59

Total/Pending/Completed Milestone - 1 / 1 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1200.21200.21771.07

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1586.34204.599.51800.43

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/02/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
2000

Ministry Review Date

LatestLastPhysical Progress (%)Status
99Ongoing

Monthly Status

Background Information

Project commissioned Work allotted to IRCON vide Railway Board s letter no. 2015/W-1/Genl/ Presentation/Pt. dated 11.12.2015. Year wise target is as under: i) Manpur - Wazirganj (18.15Km) has been commissioned in Dec 19. ii) Wazirganj -Tiliaya (17.63Km) - has been commissioned in Sep 22. iii) Lakhisarai – Sheikhpura (25.32Km) - has been commissioned in Feb 23. iv) Sheikhpura - Kashichak (15.38 Km) - commissioned in Sep 23. v) Kashichak - Warisaliganj (9.87Km) - commissioned in Jan 24. vi)Warasaliganj - Nawada (19.13km) - commissioned on 2July 2024 vii) Nawada - Tilaiya (17.32 Km) - commissioned on 5 Feb 2025 vi)Warasaliganj - Nawada (19.13km) - commissioned on 2July 2024 vii) Nawada - Tilaiya (17.32 Km) - commissioned on 5 Feb 2025 Work allotted to IRCON vide Railway Board s letter no. 2015/W-1/Genl/ Presentation/Pt. dated 11.12.2015. Year wise target is as under: a) Manpur Jn - Wazerganj (20.34Km) - has been commissioned Dec 19 b) Wazerganj - Tilaiya Junction - has been commissioned Sep 22 c) Sheikhpura Junction - Kashi Chak (15.4 km) - has been commissioned on 01/09/2023 d) Luckeesarai Junction - Sheikhpura Junction - has been commissioned Feb 23 e) Kashi Chak - Warisale Ganj - has been commissioned Jan 24 f) Warisale Ganj - Nawadah - Targeted in April 24 g) Nawadah - Tilaiya Junction - Targeted in May 24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone