Project commissioned
Work allotted to IRCON vide Railway Board s letter no. 2015/W-1/Genl/ Presentation/Pt. dated 11.12.2015. Year wise target is as under:
i) Manpur - Wazirganj (18.15Km) has been commissioned in Dec 19.
ii) Wazirganj -Tiliaya (17.63Km) - has been commissioned in Sep 22.
iii) Lakhisarai – Sheikhpura (25.32Km) - has been commissioned in Feb 23.
iv) Sheikhpura - Kashichak (15.38 Km) - commissioned in Sep 23.
v) Kashichak - Warisaliganj (9.87Km) - commissioned in Jan 24.
vi)Warasaliganj - Nawada (19.13km) - commissioned on 2July 2024
vii) Nawada - Tilaiya (17.32 Km) - commissioned on 5 Feb 2025 | Work allotted to IRCON vide Railway Board s letter no. 2015/W-1/Genl/ Presentation/Pt. dated 11.12.2015. Year wise target is as under:
a) Manpur Jn - Wazerganj (20.34Km) - has been commissioned Dec 19
b) Wazerganj - Tilaiya Junction - has been commissioned Sep 22
c) Sheikhpura Junction - Kashi Chak (15.4 km) - has been commissioned on 01/09/2023
d) Luckeesarai Junction - Sheikhpura Junction - has been commissioned Feb 23
e) Kashi Chak - Warisale Ganj - has been commissioned Jan 24
f) Warisale Ganj - Nawadah - Targeted in April 24
g) Nawadah - Tilaiya Junction - Targeted in May 24 |