Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 47.56
|
Time Overrun (Months)-
59
|
Total/Pending/Completed Milestone -
1
/
1
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
Project commissioned
Work allotted to IRCON vide Railway Board s letter no. 2015/W-1/Genl/ Presentation/Pt. dated 11.12.2015. Year wise target is as under:
i) Manpur - Wazirganj (18.15Km) has been commissioned in Dec 19.
ii) Wazirganj -Tiliaya (17.63Km) - has been commissioned in Sep 22.
iii) Lakhisarai – Sheikhpura (25.32Km) - has been commissioned in Feb 23.
iv) Sheikhpura - Kashichak (15.38 Km) - commissioned in Sep 23.
v) Kashichak - Warisaliganj (9.87Km) - commissioned in Jan 24.
vi)Warasaliganj - Nawada (19.13km) - commissioned on 2July 2024
vii) Nawada - Tilaiya (17.32 Km) - commissioned on 5 Feb 2025 vi)Warasaliganj - Nawada (19.13km) - commissioned on 2July 2024
vii) Nawada - Tilaiya (17.32 Km) - commissioned on 5 Feb 2025 | Work allotted to IRCON vide Railway Board s letter no. 2015/W-1/Genl/ Presentation/Pt. dated 11.12.2015. Year wise target is as under:
a) Manpur Jn - Wazerganj (20.34Km) - has been commissioned Dec 19
b) Wazerganj - Tilaiya Junction - has been commissioned Sep 22
c) Sheikhpura Junction - Kashi Chak (15.4 km) - has been commissioned on 01/09/2023
d) Luckeesarai Junction - Sheikhpura Junction - has been commissioned Feb 23
e) Kashi Chak - Warisale Ganj - has been commissioned Jan 24
f) Warisale Ganj - Nawadah - Targeted in April 24
g) Nawadah - Tilaiya Junction - Targeted in May 24 |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |