Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : EAST CENTRAL RAILWAYS.
Project Name : RAMPUR DUMRA - TAL - RAJENDRAPUL DOUBLING INCLUDING GANGA BRIDGE.

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    60

Total/Pending/Completed Milestone - 1 / 0 / 1

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1491.471491.471491.47

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
886.07449.67761411.74

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20200/03/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
5000

Ministry Review Date

LatestLastPhysical Progress (%)Status
77Ongoing

Monthly Status

Background Information

Embankment on North end has been completed. Boulder pitching work for slope protection is also completed. Earth work of 26.38 lakh cum completed in South end approach. Works on Well foundations of the main bridge are in various stages. Well steining at 16 locations and Piers at 8 locations & 2 abutment completed. Steining of balance 2 Wells in progress at various stages. Fabrication of steel girders for 14 spans completed and erection of 8 spans completed. Work of Minor bridges at 7 locations completed. RUB completed and opened for traffic. Foundation & substructure work of ROB - 1& 2 Completed. Erection of superstructure of ROB -2 completed. Foundation & substructure work of ROR-1,2& 3 completed. Railway viaduct 95% foundation work, 75% substructure work, 50% launching work and 33% deckslab casting completed. Shiffting of transmission lines which comes accross the alignment are under progress. Felling of trees has been completed. Total 10.3 Ha Land has been given possession on paper but villagers are protesting due to alleged in sufficient compensation. Shifting of IOCL pipeleins work is in progress.Formation work completed on North bank. Platform & station Building works in progress. Work in progress in main bridge & South end approach. Project scheduled for completion by Sep-2024.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone