Work allotted to IRCON. Physical progress- 87%. Formation work completed on North bank. Platform & station Building works in progress. Work in progress in main bridge & South end approach. 12 spans of main bridge launched. Project scheduled for completion by Dec-2025. | Embankment on North end has been completed. Boulder pitching work for slope protection is also completed. Earth work of 26.38 lakh cum completed in South end approach.
Works on Well foundations of the main bridge are in various stages. Well steining at 16 locations and Piers at 8 locations & 2 abutment completed. Steining of balance 2 Wells in progress at various stages. Fabrication of steel girders for 14 spans completed and erection of 8 spans completed.
Work of Minor bridges at 7 locations completed. RUB completed and opened for traffic. Foundation & substructure work of ROB - 1& 2 Completed. Erection of superstructure of ROB -2 completed. Foundation & substructure work of ROR-1,2& 3 completed.
Railway viaduct 95% foundation work, 75% substructure work, 50% launching work and 33% deckslab casting completed.
Shiffting of transmission lines which comes accross the alignment are under progress. Felling of trees has been completed.
Total 10.3 Ha Land has been given possession on paper but villagers are protesting due to alleged in sufficient compensation. Shifting of IOCL pipeleins work is in progress. |