Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : BARAMATI - LONAND (54 KM).

Reported Date : 09-SEP-16

MOU Status :

Monthly Report : 6 / 2016

Cost Overrun (%)-   0

Time Overrun (Months)-    N.A.

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
736.44736736

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
00128.32128.32

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20210/00/0

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
00

Ministry Review Date

LatestLastPhysical Progress (%)Status
0Ongoing

Monthly Status

Background Information

The project was approved on February 1998 with original cost Rs 75.00 crore. Anticipated cost of the project is now Rs 736.00 crore.The original date of commissioning and anticipated date of commissioning were not provided.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone