Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : WARDHA-BALHARSHAH - 3RD LINE (132 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   8.85

Time Overrun (Months)-    48

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1272.1901384.72

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
972.69427.433.571433.66

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
200452

Ministry Review Date

LatestLastPhysical Progress (%)Status
67Ongoing

Monthly Status

Background Information

Chitoda -Sonegaon 13.27km Section commissioned in April 2019. Sonegaon Hinganghat -16.17km section commissioned on 25/02/22. Sewagram-Chittoda (1.50 Km) commissioned on 29.06.2023. Balance targeted section work is in progress.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone