Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : ITARSI-NAGPUR (BAL.) - 3RD LINE (267 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   0

Time Overrun (Months)-    48

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2449.9102449.91

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1196.97411.960.161669.03

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20230/03/2027

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
720458

Ministry Review Date

LatestLastPhysical Progress (%)Status
48Ongoing

Monthly Status

Background Information

Total 99.9 Km section Teegaon- Narkher - Katol - Kohli commissioned. Kohli- Kalmeshwar-Bharatwada 22.46 Km Completed. CRS inspection done & Section commissioned on 15.03.24. Land 80.39 ha out of 115.57 Ha acquired. EPC tender for Maramjhiri to Chichonda (69.8 Km) 3rd line awarded in Aug 22. E/W in progress 17.45Lm3 done.17 Minor bridges completed. DHQ MJY 10.1km section tender awarded . EW in progress.1.75Lm3 EW done EPC-II tender for Jujharpur (km.751.1 to Dharakoh) Length 75.75km Rs. 686 Cr invited. Opened on 13.03.24

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks