Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 0
|
Time Overrun (Months)-
48
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| Total 99.9 Km section Teegaon- Narkher - Katol - Kohli commissioned. Kohli- Kalmeshwar-Bharatwada 22.46 Km Completed. CRS inspection done & Section commissioned on 15.03.24. Land 80.39 ha out of 115.57 Ha acquired. EPC tender for Maramjhiri to Chichonda (69.8 Km) 3rd line awarded in Aug 22. E/W in progress 17.45Lm3 done.17 Minor bridges completed. DHQ MJY 10.1km section tender awarded . EW in progress.1.75Lm3 EW done EPC-II tender for Jujharpur (km.751.1 to Dharakoh) Length 75.75km Rs. 686 Cr invited. Opened on 13.03.24 |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |