Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : PUNE-MIRAJ-LONDA (467 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   94

Time Overrun (Months)-    14

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
3627.4707037.24

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
3686.96728.63128.224543.81

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20240/05/2025

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
685972

Ministry Review Date

LatestLastPhysical Progress (%)Status
84Ongoing

Monthly Status

Background Information

Miraj to Londa entire work in SWR has been completed & Commissioned. On C.Rly- Sangali-Miraj-Vijaynagar section (9.23 Km) commissioned on 19.01.2024.Now Jarandeswar-Satara 7.57 Km commissioned on 31.0302024 Till date Out of 281 Kms. and 30 block section, Total 217.53 Kms. and 26 block sections have been completed & Commissioned. Further works are in progress at various locations in entire PA-MRJ section. There is a problem of land acquisition in Satara District. Therefore the project has been declared as the Railway Special Project. Out of Total 118.9238 Ha.in entire PA-MRJ section, 98.2752 Ha land has been acquired. For bal. 20.6486 is in process. Till date amount of Rs.151.21 Cr. has been deposited to State authority for land acquisition.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone