Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 94
|
Time Overrun (Months)-
14
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
3686.96 | 728.63 | 128.22 | 4543.81 |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| Miraj to Londa entire work in SWR has been completed & Commissioned. On C.Rly- Sangali-Miraj-Vijaynagar section (9.23 Km) commissioned on 19.01.2024.Now Jarandeswar-Satara 7.57 Km commissioned on 31.0302024 Till date Out of 281 Kms. and 30 block section, Total 217.53 Kms. and 26 block sections have been completed & Commissioned. Further works are in progress at various locations in entire PA-MRJ section. There is a problem of land acquisition in Satara District. Therefore the project has been declared as the Railway Special Project. Out of Total 118.9238 Ha.in entire PA-MRJ section, 98.2752 Ha land has been acquired. For bal. 20.6486 is in process. Till date amount of Rs.151.21 Cr. has been deposited to State authority for land acquisition. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |