Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 10.94
|
Time Overrun (Months)-
34
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| Manmad to Kanhegaon (57.230kms), Puntamba to Padhegaon (32.400kms),Kashti to Visapur (38.910kms) and Sarola to akolner (5.77 Kms) had been commissioned till 09.11.2023.Now Nimblak to Vambori (20.960 kms) has been commissioned on 29.02.2024.Total 155.27 kms section has been commissioned till date. Balance targeted section work is in progress. Total 58.970 Ha. out of 65.945 Ha land acquired. Balance 6.975 Ha land to be acquired. |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |