Manmad to Kanhegaon (57.230kms), Puntamba to Padhegaon (32.400kms),Kashti to Visapur (38.910kms) and Sarola to akolner (5.77 Kms) had been commissioned till 09.11.2023.Now Nimblak to Vambori (20.960 kms) has been commissioned on 29.02.2024.Total 155.27 kms section has been commissioned till date. Balance targeted section work is in progress. Total 58.970 Ha. out of 65.945 Ha land acquired. Balance 6.975 Ha land to be acquired. | Kopargaon to Yeola (13.613 km) commissioned on 04.10.2019. Yeola-Ankai (15.13 km)commissioned on 14.09.2020. Ankai - Ankai Killa (4.75 km) commissioned on 14.02.22. Ankai Killa- Manmad (8.63 km) Commissioned on 28.06.2022.Kashti to Belwandi (24.88 km) commissioned on 18/21.10.2022.Total commissioned 67.64 km out of 247.50 km. Total land of 79.086 Ha is to be acquired. out of which 7.25 Ha land acquired. |