1. For AKR-ANG-NNB section 10,786 cum of Ballast supplied.
2. For VPR-SRL section, Linking of 2100m completed.
3. Bridge work in Manmad Entry arrangement and Remaining track work in progress Total Ballast supply 10700 cum.completed. | Manmad to Kanhegaon (57.230kms), Puntamba to Padhegaon (32.400kms),Kashti to Visapur (38.910kms) and Sarola to akolner (5.77 Kms) had been commissioned till 09.11.2023.Now Nimblak to Vambori (20.960 kms) has been commissioned on 29.02.2024.Total 155.27 kms section has been commissioned till date. Balance targeted section work is in progress. Total 58.970 Ha. out of 65.945 Ha land acquired. Balance 6.975 Ha land to be acquired. |