Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : DAUND - MANMAD (236 KM).

Reported Date : 15-APR-25

Monthly Report : 5 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
2081.2702081.27

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
2629.440.9852.672723.05

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20250/01/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
268.2710.72

Ministry Review Date

LatestLastPhysical Progress (%)Status
88Ongoing

Monthly Status

Background Information

Manmad to Kanhegaon (57.230kms), Puntamba to Padhegaon (32.400kms),Kashti to Visapur (38.910kms) and Sarola to akolner (5.77 Kms) had been commissioned till 09.11.2023.Now Nimblak to Vambori (20.960 kms) has been commissioned on 29.02.2024.Total 155.27 kms section has been commissioned till date. Balance targeted section work is in progress. Total 58.970 Ha. out of 65.945 Ha land acquired. Balance 6.975 Ha land to be acquired.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks