Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : DAUND - MANMAD (236 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   10.94

Time Overrun (Months)-    21

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
187602081.27

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1266.37354.3840.161660.91

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20230/012/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
4300

Ministry Review Date

LatestLastPhysical Progress (%)Status
86Ongoing

Monthly Status

Background Information

Manmad to Kanhegaon (57.230kms), Puntamba to Padhegaon (32.400kms),Kashti to Visapur (38.910kms) and Sarola to akolner (5.77 Kms) had been commissioned till 09.11.2023.Now Nimblak to Vambori (20.960 kms) has been commissioned on 29.02.2024.Total 155.27 kms section has been commissioned till date. Balance targeted section work is in progress. Total 58.970 Ha. out of 65.945 Ha land acquired. Balance 6.975 Ha land to be acquired.Kopargaon to Yeola (13.613 km) commissioned on 04.10.2019. Yeola-Ankai (15.13 km)commissioned on 14.09.2020. Ankai - Ankai Killa (4.75 km) commissioned on 14.02.22. Ankai Killa- Manmad (8.63 km) Commissioned on 28.06.2022.Kashti to Belwandi (24.88 km) commissioned on 18/21.10.2022.Total commissioned 67.64 km out of 247.50 km. Total land of 79.086 Ha is to be acquired. out of which 7.25 Ha land acquired.

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone