Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : MANMAD - JALGAON - 3RD LINE (160 KM).

Reported Date : 14-MAY-25

Monthly Report : 6 / 2025

  

   

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1035.1601558.75

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1614.8360.7416.581692.15

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
12/20240/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
89.4380

Ministry Review Date

LatestLastPhysical Progress (%)Status
97Ongoing

Monthly Status

Background Information

Imp bridge No 293/1 at maniyar river work in progress. Kajgaaon Galan Pimperkhed FOB-Work in progress at all locations. Pimperkhed-Nandgaon (10.40 km) Section work is in progress, TDC- Aug 2025. Revised Estimate sanctioned by HQ amounting Rs 1558.75 Crs on 24-04-2025. Jalgaon – Sirsoli (11.35 km), Sirsoli – Maheji (21.54 km) & Maheji- Pachora (14.70 km) – Total 47.59 Km. CRS inspection done & section commissioned on 26/08/2022. Manmad-Nandgaon section (25.09 Km) commissioned on 24.08.2023. Pimperkhed-Chalisgaon (31.79 Kms) section commissioned on 19.03.2024. CSN-PC section work is in progress TDC- Aug 2024, NGN-PKE Section work is in progress. TDC- DEC/2024

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks