Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : MANMAD - JALGAON - 3RD LINE (160 KM).

Reported Date : 12-FEB-24

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2024

Cost Overrun (%)-   0

Time Overrun (Months)-    33

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1035.1601035.16

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
769.11153.7943.32966.22

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/012/2024

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
3500

Ministry Review Date

LatestLastPhysical Progress (%)Status
75Ongoing

Monthly Status

Background Information

Jalgaon – Sirsoli (11.35 km), Sirsoli – Maheji (21.54 km) & Maheji- Pachora (14.70 km) – Total 47.59 Km. CRS inspection done & section commissioned on 26/08/2022. Manmad-Nandgaon section (25.09 Km) commissioned on 24.08.2023. Pimperkhed-Chalisgaon (31.79 Kms) section commissioned on 19.03.2024. CSN-PC section work is in progress TDC- Aug 2024, NGN-PKE Section work is in progress. TDC- DEC/2024"Jalgaon-Sirsoli-Maheji-Pachora section (47.59 km) CRS inspection done & Section commissioned on 26/08/2022. 11.007 Ha land required in Jalgaon District in 17 villages. JM done for all and verified in Dec?18. Final award is awaited. JMR fees deposited. New additional proposal for 11 villages submitted in May-20. The possession of land 1.102 Ha acquired & balance land is yet to be received. Proposals for land acquisition of 2.75 Ha in 5 villages in Nasik District have been submitted to the District Collector of Nashik on May-21. Acquisition process for balance 2.1292 Ha Pvt land and 0.1775 Ha Govt. land to be expedited by State Govt."

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone