Imp bridge No 293/1 at maniyar river work in progress. Kajgaaon Galan Pimperkhed FOB-Work in progress at all locations.
Pimperkhed-Nandgaon (10.40 km) Section work is in progress, TDC- Aug 2025.
Revised Estimate sanctioned by HQ amounting Rs 1558.75 Crs on 24-04-2025. | Jalgaon – Sirsoli (11.35 km), Sirsoli – Maheji (21.54 km) & Maheji- Pachora (14.70 km) – Total 47.59 Km. CRS inspection done & section commissioned on 26/08/2022. Manmad-Nandgaon section (25.09 Km) commissioned on 24.08.2023. Pimperkhed-Chalisgaon (31.79 Kms) section commissioned on 19.03.2024. CSN-PC section work is in progress TDC- Aug 2024, NGN-PKE Section work is in progress. TDC- DEC/2024 |