Project Summary
Project Summary
Sector Name : RAILWAYS.
Agency Name : CENTRAL RAILWAYS.
Project Name : MANMAD - JALGAON - 3RD LINE (160 KM).

Reported Date : 13-FEB-25

MOU Status : Project Under MOU for 2017-2018

Monthly Report : 3 / 2025

Cost Overrun (%)-   50.58

Time Overrun (Months)-    48

Total/Pending/Completed Milestone - 0 / 0 / 0

Cost (Rs. in Crores)

OriginalRevisedNow Anticipated
1035.1601558.75

Expenditure (Rs. in Crores)

Cum. till Previous Financial YearCum. in Current Financial Year till last monthExpenditure in current monthCum. Expenditure till now
1190.84361.5162.481614.83

Date of Commissioning (mm/yyyy)

OriginalRevisedAnticipated
3/20220/03/2026

Current Financial Year Budget (Rs. in Crores)

Budget EstimateRevised Estimate
250380

Ministry Review Date

LatestLastPhysical Progress (%)Status
80Ongoing

Monthly Status

Background Information

Jalgaon – Sirsoli (11.35 km), Sirsoli – Maheji (21.54 km) & Maheji- Pachora (14.70 km) – Total 47.59 Km. CRS inspection done & section commissioned on 26/08/2022. Manmad-Nandgaon section (25.09 Km) commissioned on 24.08.2023. Pimperkhed-Chalisgaon (31.79 Kms) section commissioned on 19.03.2024. CSN-PC section work is in progress TDC- Aug 2024, NGN-PKE Section work is in progress. TDC- DEC/2024

Problems

ProblemStart (mm/yyyy)End (mm/yyyy)StatusAttention RequiredRemarks

Ongoing Milestone

Completed Milestone