Reported Date :
13-FEB-25
|
MOU Status :
Project Under MOU for 2017-2018
|
Monthly Report :
3
/
2025
|
Cost Overrun (%)- 50.58
|
Time Overrun (Months)-
48
|
Total/Pending/Completed Milestone -
0
/
0
/
0
|
Original | Revised | Now Anticipated |
Expenditure (Rs. in Crores)
|
|
Cum. till Previous Financial Year | Cum. in Current Financial Year till last month | Expenditure in current month | Cum. Expenditure till now |
1190.84 | 361.51 | 62.48 | 1614.83 |
Date of Commissioning (mm/yyyy)
|
|
Original | Revised | Anticipated |
Current Financial Year Budget (Rs. in Crores)
|
|
Budget Estimate | Revised Estimate |
Latest | Last | Physical Progress (%) | Status |
Monthly Status
|
Background Information
|
|
| Jalgaon – Sirsoli (11.35 km), Sirsoli – Maheji (21.54 km) & Maheji- Pachora (14.70 km) – Total 47.59 Km. CRS inspection done & section commissioned on 26/08/2022. Manmad-Nandgaon section (25.09 Km) commissioned on 24.08.2023. Pimperkhed-Chalisgaon (31.79 Kms) section commissioned on 19.03.2024. CSN-PC section work is in progress TDC- Aug 2024, NGN-PKE Section work is in progress. TDC- DEC/2024 |
Problem | Start (mm/yyyy) | End (mm/yyyy) | Status | Attention Required | Remarks |
| Ongoing Milestone | | Completed Milestone | | |